Aerial view of the completed 16.15 kW solar array on the Mansfield Heritage Museum roof

Mansfield Heritage Museum: 16.15 kW Solar and a 55.68 kWh Battery

A council build in regional Victoria, sized around what the building draws overnight rather than what fits on the roof.

Project · Mansfield, Victoria

E3 Energy designed, supplied and installed a 16.15 kW solar system and a 55.68 kWh FOX ESS battery for the new Mansfield Heritage Museum, a Mansfield Shire Council project completed in June 2026. This is how the job was scoped, installed and commissioned.

Aerial view of the completed 16.15 kW solar array on the Mansfield Heritage Museum roof
The finished array on the Mansfield Heritage Museum. The museum forms part of the Station Precinct redevelopment in Mansfield.

The building

The Mansfield Heritage Museum is a new rammed-earth building in the Station Precinct on High Street, Mansfield. It has been a long time coming: the Mansfield Historical Society had been calling for a museum in the town for more than forty years, and a local fundraising appeal that raised $114,000 went on to attract more than $1 million in grant funding to get the building to lock-up stage in 2024. The wider Station Precinct redevelopment, which also covers a dog park, playground, car parks and upgrades to the old Goods Shed, is backed by a $14 million Federal grant administered by Mansfield Shire Council.

The museum is expected to open to the public in late 2026 or early 2027. The energy system needed to be in place before the fit-out and the exhibits went in.

The Mansfield Heritage Museum site before the solar and battery installation
The site before installation. The new museum building sits alongside the heritage station buildings.

Why this site needed storage

A museum is not a nine-to-five building. Collections need stable temperature and humidity, which means climate control runs through the night and through the weekend, when there is no sun and no staff on site. A solar-only system would have generated well during the day and left the overnight load on the grid.

Mansfield is also a regional site. Outages in country Victoria are more common and last longer than they do in metropolitan Melbourne, and a building holding irreplaceable local artefacts is a poor candidate for an unplanned loss of climate control.

Those two facts drove the design: enough generation to cover the daytime load with margin, and enough storage to carry the building through the night and hold it up during an outage.

The system

Component Specification
Solar array 16.15 kW
Battery storage FOX ESS, 55.68 kWh
Site Mansfield Heritage Museum, Mansfield VIC
Client Mansfield Shire Council
Completed 13 June 2026

The 55.68 kWh battery is a large bank for a building of this size. That is deliberate. Sizing storage to the overnight load rather than to a package tier is the difference between a battery that runs flat at 2am and one that still has capacity when the sun comes up.

Install: rails, then panels

The roof is new Colorbond on a steel frame, which made the mounting straightforward. Rails went down first, set out and fixed to the roof structure rather than to the sheeting alone.

E3 Energy installer fixing mounting rails to the museum roof
Setting out and fixing the mounting rails. Getting this stage right is what stops a roof leaking in five years’ time.

Panels followed across two roof planes, laid out to keep the array clear of the skylights and roof penetrations.

Two CEC-accredited E3 Energy installers fitting solar panels on the museum roof
Our own CEC-accredited installers on the roof. E3 does not subcontract its installs.
The E3 Energy install team laying solar panels at the Mansfield Heritage Museum
The array went down across two planes over a single day on the roof.

Electrical and commissioning

The FOX ESS inverter and battery were mounted on the external wall in the plant area, with the switchboard and isolators run in conduit back to the building’s main board.

E3 Energy electrician wiring the FOX ESS inverter at the Mansfield Heritage Museum
Wiring the FOX ESS inverter.
The commissioned FOX ESS battery and switchboard at the Mansfield Heritage Museum
The commissioned system. Signage, isolation and labelling to standard: the part nobody photographs, and the part an electrical inspector actually looks at.

Handover

The system was handed over to Mansfield Shire Council in June 2026, ahead of the museum’s internal fit-out. Council has since invited E3 Energy to tender for further work in the Mansfield Shire.

E3 Energy team on site with Mansfield Shire representatives at handover
On site at handover.
The Mansfield Heritage Museum and Station Precinct with the new rooftop solar system
The museum in the wider Station Precinct.

What this means if you run a similar site

Community buildings, council facilities, clubs and small commercial sites tend to share the same shape of problem: a daytime load that solar covers easily, and a base load overnight that solar does nothing for. On sites like these, the battery size is usually what decides whether the numbers work.

We size both from your actual interval data, not from a package menu. If you have twelve months of bills, we can tell you what a system would do before you commit to anything.

Commercial or council site?
Send us twelve months of bills and we’ll size it properly.

Book your free energy assessment

Common questions

How big a battery does a commercial site actually need?

It depends on your overnight and weekend load, not on your roof size or your daytime consumption. A site that shuts down at 5pm needs far less storage than one running climate control or refrigeration around the clock. We read it off your interval data.

Does E3 work with councils and government projects?

Yes. The Mansfield Heritage Museum was delivered for Mansfield Shire Council. We hold the accreditations required for public works and can supply the documentation councils need for procurement.

Do you subcontract your installs?

No. Our own CEC-accredited team does the install and the commissioning, and the same team handles service afterwards.

Can a battery keep a building running during an outage?

With the right configuration, yes, for the loads you nominate as essential. This matters more in regional Victoria, where outages are longer and more frequent than in metropolitan Melbourne.

Installed and commissioned by E3 Energy (E Cubic Pty Ltd), CEC-accredited solar and battery installers serving Melbourne and regional Victoria.